May 12th 2021 Live news feed - Regent Plaza, Manchester - Piling commences for Block D
*************
May 10th 2021 Live news feed - Regent Plaza, Manchester - Block C - steel frame will be completed this week
*************
May 10th 2021 Live news feed - Regent Plaza, Manchester - Block B - partitions installed to levels 9, 8, 7 and 6
*************
May 10th 2021 Live news feed - Regent Plaza, Manchester - Block B - windows installed to levels 6 and 7
*************
May 10th 2021 Live news feed - Regent Plaza, Manchester - Block C - metal decking to the 1st, 2nd, 3rd, 4th, 5th and 6th floors
*************
May 10th 2021 Live news feed - Derby Court, Liverpool - Steel frame completed - concrete floor installation commences
*************
April 8th 2021 Live news feed - Regent Plaza, Manchester - Window installation nears completion on floors 8 and 9
*************
April 8th 2021 Live news feed - Regent Plaza, Manchester - Block C steel frame erection works ongoing
*************
April 8th 2021 Live news feed - Derby Court, Liverpool - Under slab drainage works ongoing
*************
April 8th 2021 Live news feed - Derby Court, Liverpool - Metal deck and concrete floors - work commences
*************
April 8th 2021 Live news feed - Derby Court, Liverpool - Steel frame erection complete
*************
March 18th 2021 Live news feed - Regent Plaza, Manchester - Block B window installation commences
*************
March 18th 2021 Live news feed - Regent Plaza, Manchester - Block C steel frame arrives Thursday 18th March
*************
March 10th 2021 Live news feed - Regent Plaza, Manchester - Block C steel frame delivery scheduled for Thursday 18th March
*************
March 8th 2021 Live news feed - Derby Court, Liverpool - Steel frame is delivered to site and assembly has commenced
*************
March 5th 2021 Live news feed - Regent Plaza, Manchester - Muck shift continues to completion during March 2021
*************
March 4th 2021 Live news feed - Regent Plaza, Manchester - Block B internal drainage works underway
*************
March 3rd 2021 Live news feed - Regent Plaza, Manchester - Block C cropping piles underway
*************
March 5th 2021 Live news feed - Derby Court, Liverpool - Concrete foundations poured including lift pit completion expected w/c 08.03.21
*************
February 19th 2021 Live news feed - Derby Court, Liverpool - Steel frame and pre-cast stairs due for installation 01.03.21
*************
February 19th 2021 Live news feed - Derby Court, Liverpool - Site contractor has dug and poured the mass fill for 21 out of 25 of the perimeter foundations
*************
February 19th 2021 Live news feed - Regent Plaza, Manchester - Block B internal blockwork commences 22.02.21
*************
February 19th 2021 Live news feed - Regent Plaza, Manchester - Block B window installation due to commence 08.03.21
*************
February 19th 2021 Live news feed - Regent Plaza, Manchester - Block B - Glassroc x weather boarding commences 22.02.21
*************
February 19th 2021 Live news feed - Regent Plaza, Manchester - Block B external perimeter drainage works ongoing.
*************
February 19th 2021 Live news feed - Regent Plaza, Manchester - Block C steel frame fabrication underway.
*************
February 19th 2021 Live news feed - Regent Plaza, Manchester - Block C piling work continues.
*************
February 19th 2021 Live news feed - Regent Plaza, Manchester - Block B roof installation well underway and due for completion in 6 weeks.
*************
February 16th 2021 Live news feed - Regent Plaza, Manchester - Block B external SFS expected to be completed by end of February 2021.
*************
February 17th 2021 Live news feed - Regent Plaza, Manchester - Main earth shift underway across entire site.
*************
February 15th 2021 Live news feed - Regent Plaza, Manchester - Mast climbers and hoist installed on Block B with works progressing well into February.
*************
January 25th 2021 Live news feed - Sourced Development Group ground works on Derby Court Liverpool are commencing with steel frame due for delivery in early March 2021.
*************
January 19th 2021 Live news feed - Sourced Development Group announce contract award to Nationwide Management Services Group across all North West sites.
*************
January 7th 2021 Live news feed - Sourced Development Group submit pre-planning application for new residential scheme Carlton Court, Liverpool - GDV approximately £36M.
*************
January 6th 2021 Live news feed - Block C Steel Frame confirmed to arrive on site by end of February 2021
*************
January 4th 2021 Live news feed - Swanside Group return to site at Regent Plaza, Manchester to recommence works after Christmas and New Year break. Work continues in accordance with UK rules in Tier 5.
*************
January 4th 2021 Live news feed - Block C Steel Frame set to arrive on site at Regent Plaza, Manchester 2 months ahead of schedule.
*************
December 25th 2020 Live news feed - Sees uXO /Piling mat now 100% completed at Regent Plaza, Manchester.