Regent Plaza: Live News Jan - May 2021

Updated: Oct 14, 2021

May 12th 2021

Piling commences for Block D

May 10th 2021

Block C - Steel frame will be completed this week.

Block B - Partitions installed to levels 9, 8, 7 and 6.

Block B - Windows installed to levels 6 and 7.

Block C - Metal decking to the 1st, 2nd, 3rd, 4th, 5th and 6th floors April 8th 2021

Window installation nears completion on floors 8 and 9.

Block C steel frame erection works ongoing Block C steel frame erection works ongoing March 18th 2021

Block B window installation commences Block C steel frame arrives Thursday 18th March

March 10th 2021

Block C steel frame delivery scheduled for Thursday 18th March March 5th 2021

Muck shift continues to completion during March 2021

March 4th 2021

Block B internal drainage works underway March 3rd 2021

Block C cropping piles underway


February 19th 2021

Block B internal blockwork commences 22.02.21 Block B window installation due to commence 08.03.21 Block B - Glassroc x weather boarding commences 22.02.21 Block B external perimeter drainage works ongoing. Block C steel frame fabrication underway. Block C piling work continues. Block B roof installation well underway and due for completion in 6 weeks. Block B external SFS expected to be completed by end of February 2021.

February 17th 2021

Main earth shift underway across entire site. Mast climbers and hoist installed on Block B with works progressing well into February.

January 19th 2021

Sourced Development Group announce contract award to Nationwide Management Services Group across all North West sites.